Remodel estimate calculator

Small remodel quotes mix hours, unit repairs, a materials allowance, and a dumpster or skip. This calculator keeps those lines and the markup visible.

Start a remodel estimate

Overhead and profit

Overhead is a percent of the line items. Profit is a percent of the subtotal plus overhead. They are separate so you can explain them, or set either one to zero.

The deposit is a percent of the total after tax. The sample uses 30%. Use the deposit you actually collect.

Worked example

A small example: demo hours, drywall, paint, carpentry, a materials allowance at 15% markup, and a dumpster. Not a whole-house bid.

  • Demo and protection$420.00
  • Drywall repair$260.00
  • Paint$440.00
  • Carpentry labor$375.00
  • Materials allowance$368.00
  • Dumpster$185.00

Example total after overhead, profit, and tax: $2,478.08. Deposit at 30%: $743.42.